Scope of Work
Renewable energy system panning 11,000 acres of G-1 grazing land, this project consists of 57 Vestas 2.1 MW turbines, a 167,000 linear foot collection system, 7 miles of transmission line, a 161 kV substation and a 7,200 square foot O&M building. This 120MW wind farm is located in Bonneville County, Idaho.
Services Employed
- Turbine Erection
- Foundations
- Collection System
- SCADA
- Substation System
- Transmission Lines
- O&M Building